When a compressor equipment schedule leaves out selection requirements, submit an RFI that identifies the missing information, cites the affected documents, and asks for a specific design decision. Don’t fill the blanks with a supplier’s standard package or an estimator’s assumption. Explain what cannot be selected or priced reliably until the project team responds.
A useful compressor equipment schedule RFI separates design requirements from supplier recommendations. The engineer establishes the required duty and acceptance criteria; the equipment supplier can then propose a package against that basis. At Process & Power, we can help review the equipment requirements for a quotation, but our proposal does not replace the project’s design clarification or approval process.
Check Whether the Information Is Missing or Conflicting
Before drafting the RFI, compare the equipment schedule with the current specifications, plans, details, and addenda. A schedule may omit dryer requirements that appear in the compressed air specification. Conversely, a schedule and specification may call for different package configurations.
Reference the exact equipment tag, drawing number, specification section, and revision involved. If documents conflict, quote both requirements and ask which governs rather than choosing the less expensive interpretation.
Also distinguish a missing design requirement from a missing product detail. Required system flow is a design input. The dimensions of a proposed compressor are typically supplier information developed after a selection basis exists. An RFI should request the former, not ask the engineer to complete a vendor’s quotation.
Ask for Requirements That Actually Change the Selection
“Please provide compressor information” is too broad. Identify the unresolved inputs and explain why they matter.
Flow, pressure, and operating duty
Required flow: Ask for the design demand, its stated measurement basis, and whether it represents average, peak, or continuous demand. A flow number without a basis may not be directly comparable to a published compressor rating.
Required pressure: Clarify whether the requirement applies at compressor discharge, after air treatment, or at the point of use. Dryer, filter, and distribution losses affect the discharge pressure needed.
Demand profile: Confirm operating hours, intermittent loads, and any documented future expansion allowance. Don’t add an arbitrary capacity margin.
Redundancy: For multiple-unit packages, ask whether scheduled capacity is total installed capacity or capacity available with a unit out of service.
Horsepower alone is not a complete selection basis. Likewise, a component’s rated output does not establish the flow and pressure available through the installed system.
Air quality and package boundaries
Ask for the required air quality at the application, including moisture, particulate, and oil requirements where relevant. Clarify the required pressure dew point—the temperature at which moisture would begin condensing at operating pressure—and the intended measurement location. Don’t assume an oil-free compressor alone satisfies every air quality requirement.
If package scope is unclear, ask whether the supply includes the dryer, filters, receiver, drains, condensate management, and package controls. These items change both equipment pricing and connection responsibilities.
Site and interface requirements
Request unresolved electrical service information, indoor or outdoor conditions, ambient design conditions, space restrictions, and ventilation provisions when they affect selection. For controls, clarify whether the package operates independently or must coordinate with existing compressors or a facility control system.
Equipment supply is not the same scope as piping installation, electrical work, controls integration, testing, or startup. Ask who carries each unresolved responsibility rather than assuming it belongs to the equipment supplier.
Use an RFI Format the Engineer Can Answer
Keep each RFI focused on a related decision. If your project separates electrical, mechanical, and controls reviews, use coordinated requests rather than one long question that crosses every discipline. The following template can be adapted to the actual gaps.
Subject: Compressor [equipment tag] — missing selection basis
Project: [Project name and Tennessee location]
References: [Drawing and revision, schedule, specification section, applicable addenda]
Documented requirement: [Quote the relevant schedule entry or specification language]
Missing or conflicting information: [Identify the specific omission or conflict]
Clarification requested: Confirm required flow and its basis; required pressure and reference location; operating duty; and standby capacity requirements, as applicable.
Related package decision: Confirm unresolved air treatment, receiver, controls, or accessory requirements and their supply boundaries.
Bid impact: Without this information, [identify the affected selection, package scope, electrical coordination, or pricing item] cannot be finalized.
Response needed: [Date tied to the equipment quotation deadline and contractor bid deadline]
Attachments: [Marked schedule excerpt, relevant specification pages, and concise comparison of conflicting requirements]
Contact: [Estimator or project manager name and contact information]
Replace general prompts with direct questions before submitting. “Confirm whether the dryer is included in the compressor package or furnished separately” is easier to answer than “Clarify all accessories.” Submit through the project’s designated RFI channel so the response becomes part of the documented record.
Example: Total Capacity or Standby Capacity?
Consider a hypothetical facility expansion in West Tennessee. The schedule identifies a multiple-compressor package and a total flow requirement, but it does not state whether that flow must remain available with one compressor out of service.
One supplier prices all compressors operating together. Another includes additional capacity for standby duty. Those quotations are not equivalent, even if both reference the same equipment tag.
The useful RFI asks: “Does the scheduled flow represent total installed capacity, or required available capacity with one compressor out of service? Please confirm the required operating and standby arrangement.” The contractor should not decide the owner’s redundancy requirement by selecting the lower quotation.
Keep Open Questions Visible in the Bid
If the response won’t arrive before pricing is needed, ask whether the bid instructions permit a qualified budget allowance or separately identified options. Any temporary pricing basis should be explicit, traceable, and subject to clarification—not buried in a general exclusion.
Label preliminary pricing: A budget based on unresolved requirements is not a firm equipment proposal against a complete selection basis.
Track affected costs: A clarification may change the compressor, air treatment, electrical requirements, or installation scope.
Separate alternates from approvals: A supplier-proposed alternate is not an engineer-approved substitution. Follow the specified review process.
Reconcile the response: Send the formal clarification and applicable addenda to quoting suppliers, then request revised proposals identifying the documents used.
Avoid treating silence as acceptance of an assumption. Before comparing final quotations, verify that each supplier is pricing the same clarified duty and package boundaries.
Send the Schedule and the Open Questions Together
Working through an incomplete compressor schedule? Send us the project scope, current schedule and specifications, open RFIs, bid deadline, project location, and estimator or project manager contact through our Contractor Bids page. Include the required-on-site date if available. We can discuss the information needed for equipment pricing and how to include us in relevant bid invitations.